EPA v. D&F ALFONSO BUILDERS (BLACK BEAR CONDO CONSTRUCTION)
Case summary
On July 10, 2025, EPA filed a Consent Agreement and Final Order with D & F Afonso Builders, Inc. ( D & F ) for discharges of stormwater without authorization under the National Pollutant Discharge Elimination System (NPDES) Construction General Permit (CGP) for Stormwater Discharges from Construction Activities. EPA conducted an inspection of D & F's residential development in Milford, Massachusetts on December 10, 2024. In addition to noting that the developer did not have CGP coverage, EPA identified several deficiencies at the site, including failed silt fences on the perimeter, and stockpiles and other slopes that were not stabilized. D & F will pay a penalty of $32,550. After EPA's inspection, D & F obtained CGP coverage. The Region coordinated with the Massachusetts Department of Environmental Protection on this case.
Defendants (1)
- D&F Afonso Builders Inc.Named in complaintNamed in settlement
Facilities (1)
BLACK BEAR CONDO CONSTRUCTION
29 CASEY DRIVE, MILFORD, MA, 01757
Registry ID: 110071885239
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
D&F ALFONSO BUILDERS (BLACK BEAR CONDO CONSTRUCTION)entered 2025-07-10
Primary law: CWA
Federal penalty: $32,550
Timeline (3 milestones)
- 2025-07-10Enforcement Action Data Entered
- 2025-07-10Complaint Filed/Proposed Order
- 2025-07-10Final Order Issued
Case metadata
- EPA activity ID
- 3604455035
- Case number
- 01-2025-2074
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit