Skip to main content
01-2025-0002Administrative - FormalFinal Order IssuedFY 2025· Region 01

EPA v. DUMMERSTON ORCHARD REMOVAL SITE

Case summary

Pursuant to Section 104 of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 ( CERCLA ), 42 U.S.C. 9604, EPA performed an emergency response removal action to address a release or threat of release of pesticides, including hazardous substances, pollutants, and contaminants at the Dummerston Orchard Site related to a fire at the Site. On September 16, 2025, EPA signed an Administrative Settlement Agreement and Order on Consent under which the orchard agreed to perform the transportation and disposal of hazardous substances, pollutants, and contaminants at the Site under EPA oversight.

Defendants (2)

  • Dwight Read Miller IIINamed in settlement
  • Dwight Miller OrchardsNamed in complaintNamed in settlement

Facilities (1)

  • DUMMERSTON ORCHARD

    193 MILLER ROAD, EAST DUMMERSTON, VT, 05346

    Registry ID: 110071818864

Statutes cited

  • CERCLA 106AImminent & Substantial Endangerment Order
  • CERCLA 122AAgreement to Perform Work Under 104B
  • CERCLA 107ACost Recovery

Enforcement conclusions (1)

  • DUMMERSTON ORCHARD REMOVAL SITEentered 2025-09-16

    Primary law: CERCLA

Timeline (3 milestones)

  • 2025-09-16Enforcement Action Data Entered
  • 2025-09-16Final Order Issued
  • 2025-09-16Complaint Filed/Proposed Order

Case metadata

EPA activity ID
3604526895
Case number
01-2025-0002
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
Imminent & Substantial Endangerment Order

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2025-0002 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.