Skip to main content
01-2023-2035Administrative - FormalClosedFY 2023· Region 01

EPA v. MCI - CONCORD

Final Order No Penalty

Case summary

On July 5, 2023, EPA issued a Clean Water Act (CWA) administrative order to MCI - Concord's Concord Massachusetts facility for failure to submit discharge monitoring reports (DMRs) pursuant to their CWA National Pollutant Discharge Elimination System (NPDES) permits. MCI - Concord is authorized to discharge under the Multi-Sector General Permit. The permittee is required to submit all outstanding DMRs and continue to report as required by their permit. MCI - Concord is located in an Environmental Justice area of concern. EPA will notify the Massachusetts Department of Environmental Protection of our actions.

Defendants (1)

  • MCI - ConcordNamed in complaintNamed in settlement

Facilities (1)

  • MCI - CONCORD

    965 ELM STREET, CONCORD, MA, 01742

    Registry ID: 110009588650

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • MCI - CONCORDentered 2023-07-05

    Primary law: CWA

Timeline (5 milestones)

  • 2023-07-05Final Order Issued
  • 2023-07-05Complaint Filed/Proposed Order
  • 2023-07-10Enforcement Action Data Entered
  • 2023-08-05NPDES Closed
  • 2023-08-05Enforcement Action Closed

Case metadata

EPA activity ID
3603645635
Case number
01-2023-2035
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2023-2035 . Bulk data: ICIS-FEC download summary.