EPA v. GREENWOOD II
Case summary
On May 4, 2022, EPA entered into an expedited settlement agreement (Agreement) with Martelli Construction Co., Inc. that addressed violations of the Clean Water Act's General Permit for Discharges from Construction Activities (CGP) at the Greenwood II site in Holden, Massachusetts. An EPA inspection at the Greenwood II site determined that the operator had failed to stabilize portions of the site and failed to maintain perimeter controls as required by the CGP. Pursuant to the Agreement, Martelli Construction Co., Inc. will pay a $10,500 penalty. EPA implements the National Pollutant Discharge Elimination System program in Massachusetts. The case team consulted with the Massachusetts Department of Environmental Protection on this matter.
Defendants (1)
- Martelli Construction Co.Named in complaintNamed in settlement
Facilities (1)
GREENWOOD II
UNION STREET, HOLDEN, MA, 01520
Registry ID: 110070382960
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
GREENWOOD IIentered 2022-05-04
Primary law: CWA
Federal penalty: $10,500
Timeline (3 milestones)
- 2022-05-04Final Order Issued
- 2022-05-04Complaint Filed/Proposed Order
- 2022-05-06Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603133984
- Case number
- 01-2022-2014
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations