EPA v. E P MANAGEMENT CORP
Case summary
On July 22, 2020, Region 1 filed an Expedited Settlement Agreement under TSCA's Lead-Based Paint Expedited Settlement Agreement Policy, resolving violations of the Renovation, Repair and Painting (RRP) Rule alleged against E.P. Management, Corp. of Beverly, Massachusetts. An EPA inspection revealed that the facility was not in full compliance with the RRP Rule. Respondent has paid a penalty of $1,000 and has come into compliance with the RRP Rule.
Defendants (1)
- E P Management Corp.Named in complaintNamed in settlement
Facilities (1)
E P MANAGEMENT CORP
142 MERCHANTS ROW, RUTLAND, VT, 05701
Registry ID: 110070566529
Statutes cited
- TSCA 402C — Lead: RRP
Enforcement conclusions (1)
E P MANAGEMENT CORPentered 2020-07-22
Primary law: TSCA
Federal penalty: $1,000
Timeline (3 milestones)
- 2020-07-22Complaint Filed/Proposed Order
- 2020-07-22Final Order Issued
- 2020-08-07Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3602253842
- Case number
- 01-2020-7009
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- Lead: RRP