On December 5, 2019, EPA Region 1 filed an expedited settlement agreement concerning Wall Street Development Corporation. The agreement addresses Wall Street Development Corporation's failure to obtain permit coverage under the General Permit for Discharges from Construction Activities (CGP) for its Boyden Estates site in Walpole, MA. It's EPA's understanding that Wall Street Development Corporation has since taken action to address its noncompliance and has obtained CGP coverage. Pursuant to the agreement, Wall Street Development Corporation will pay a $7,020 penalty. EPA implements the National Pollutant Discharge Elimination System program in Massachusetts. The case team sent a notification to the Massachusetts Department of Environmental Protection regarding the settlement of this matter.
Defendants (1)
- WALL STREET DEVELOPMENT CORP.Named in complaintNamed in settlement
Facilities (1)
BOYDEN ESTATES
325 SUMMER STREET, SOUTH WALPOLE, MA, 02071
Registry ID: 110070556070
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
WALL STREET DEVELOPMENT CORP.entered 2019-12-05
Primary law: CWA
Federal penalty: $7,020
Timeline (3 milestones)
- 2019-12-05Complaint Filed/Proposed Order
- 2019-12-05Final Order Issued
- 2019-12-09Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3602060259
- Case number
- 01-2020-2005
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit