Skip to main content
01-2019-2038Administrative - FormalFinal Order IssuedFY 2019· Region 01

EPA v. RUSSO BROS INC

Final Order With Penalty

Case summary

On June 26, 2019, Region 1 filed a Clean Water Act Expedited Settlement Agreement with Russo Bros. Inc., the site contractor at a property in Bellingham, Massachusetts that is being developed into small residential condominiums. Based on a site inspection, Region 1 determined that Russo Bros. Inc. had failed to meet sediment control requirements at the site, in violation of the National Pollutant Discharge Elimination System (NPDES) General Permit for Discharges from Construction Activities. Russo Bros. Inc. addressed its noncompliance shortly following the Region 1 inspection. The company will pay a penalty of $1,800. While EPA implements the NPDES program in Massachusetts, the case team did send notification to the Massachusetts Department of Environmental Protection of this matter.

Defendants (1)

  • Russo Bros IncNamed in complaintNamed in settlement

Facilities (1)

  • HARTFORD VILLAGE PHASE II

    HIXON STREET, BELLINGHAM, MA, 02019

    Registry ID: 110070237090

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • RUSSO BROS INCentered 2019-06-26

    Primary law: CWA

    Federal penalty: $1,800

Timeline (3 milestones)

  • 2019-06-26Complaint Filed/Proposed Order
  • 2019-06-26Final Order Issued
  • 2019-07-15Enforcement Action Data Entered

Case metadata

EPA activity ID
3601903660
Case number
01-2019-2038
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2019-2038 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.