Case summary

On February 28, 2019, EPA issued an Administrative Order (Order) against the Town of Hopedale, MA regarding the Town's Municipal Separate Storm Sewer System (MS4). The Order require the Town to submit a Notice of Intent (NOI) to be covered under the 2016 Massachusetts Small Municipal Separate Storm Sewer General Permit or an application for an individual NPDES permit by April 1, 2019. The Order does not include a penalty. The Town's NOI submittal weas due October 1, 2018. As of the date of the Order, the Town has not submitted the required NOI or an individual NPDES permit application. Although EPA has primacy for the NPDES program in Massachusetts, MassDEP supports EPA's action in this matter.

Defendants (1)

  • Hopedale Town ofNamed in complaintNamed in settlement

Facilities (1)

  • HOPEDALE TOWN OF

    78 HOPEDALE STREET, HOPEDALE, MA, 01747

    Registry ID: 110044236902

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • HOPEDALE TOWN OFentered 2019-02-28

    Primary law: CWA

Timeline (3 milestones)

  • 2019-02-28Final Order Issued
  • 2019-02-28Complaint Filed/Proposed Order
  • 2019-04-15Enforcement Action Data Entered

Case metadata

EPA activity ID
3601806182
Case number
01-2019-2026
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2019-2026 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.