Skip to main content
01-2018-7014Administrative - FormalFinal Order IssuedFY 2018· Region 01

EPA v. CAMPOS CONSTRUCTION LLC

Case summary

On March 15, 2019, EPA Region 1 filed a CAFO settling claims for civil penalties against Campos Construction for violating TSCA by failing to comply with the Renovation, Repair and Painting Rule (�RRP Rule�) while renovating two rental properties in Portland, Maine. The settlement calls for the payment of a $4,860 penalty based upon the �Pilot Graduated Penalty Approach for TSCA RRP Rule and Abatement Rule Enforcement Actions.� To promote compliance, Campos Construction has also agreed to provide reports to EPA documenting its compliance with the RRP Rule during the six-month period between April 1, 2019 and September 30, 2019. The Maine Department of Environmental Protection conducted joint inspections with EPA and supported EPA in development of the enforcement case. Maine did not take delegation of the RRP Rule. This action will help to prevent young children from being exposed to the dangers of lead paint. On September 28, 2018, Region 1 issued an administrative Complaint against Campos Construction of Portland, Maine, for alleged violations of the Renovation, Repair and Painting (RRP) Rule under TSCA at two properties in Portland, ME. The Complaint alleges that Campos Construction: (1) failed to ensure that a certified renovator was performing or directing work as required by 40 C.F.R. 745.89(d)(1); (2) failed to cover the ground with impermeable material to collect paint debris as required by 40 C.F.R. 745.85(a)(2)(ii)(C); (3) failed to contain waste from both exterior and interior renovation activities as required by 40 C.F.R. 745.85(a)(4)(i) and 745.85(a)(2), respectively; (4) failed to clean the work area after completing the renovation in violation of 40 C.F.R. 745.85(a)(5); and (5) failed to provide an acknowledgement of the property owner's receipt of the Renovate Right pamphlet as required by 40 C.F.R. 745.86(a). The proposed penalty is $37,025. The Maine Department of Environmental Protection conducted joint inspections and supported EPA in development of the enforcement case. Maine did not take delegation of the RRP Rule. This action will help to prevent young children from being exposed to the dangers of lead paint.

Defendants (1)

  • Campos Construction LLCNamed in complaintNamed in settlement

Facilities (2)

  • CAMPOS CONSTRUCTION LLC

    124-126 EMERY STREET, PORTLAND, ME, 04241

    Registry ID: 110069998985

  • CAMPOS CONSTRUCTION LLC

    1 CUMBERLAND ST, PORTLAND, ME, 04102

    Registry ID: 110070378107

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • CAMPOS CONSTRUCTION LLCentered 2019-03-15

    Primary law: TSCA

    Federal penalty: $4,861

Timeline (3 milestones)

  • 2018-09-28Complaint Filed/Proposed Order
  • 2018-10-02Enforcement Action Data Entered
  • 2019-03-15Final Order Issued

Case metadata

EPA activity ID
3601583955
Case number
01-2018-7014
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
Lead: RRP

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2018-7014 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.