EPA v. ELY COPPER MINE
Final Order No Penalty
Case summary
The settling parties are Green Crow Corporation (Green Crow), owner of property overlying underground mine tunnels, and Dwight Hill Forest, LLC (Dwight Hill), a newly-created entity that will take title to the property currently owned by Ely Mine Forest, Inc. (EMFI). The proposed Settlement Agreement requires: (1) transfer of the EMFI property to Dwight Hill; (2) provision of access and imposition of institutional controls on a site-wide basis; (3) provision to EPA of a convenient source of borrow material, thereby saving EPA the cost of purchasing clean fill; and (4) maintenance and monitoring activities on the EMFI property.
Defendants (1)
- ELY COPPER MINE (SB)Named in settlement
Facilities (1)
ELY COPPER MINE
1515 S VERSHIRE RD, VERSHIRE, VT, 05079
Registry ID: 110009347055
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
ELY COPPER MINEentered 2016-04-25
Primary law: CERCLA
Timeline (2 milestones)
- 2016-04-25Final Order Issued
- 2016-06-30Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3600748922
- Case number
- 01-2016-0007
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2016-0007 . Bulk data: ICIS-FEC download summary.