EPA v. SOMERSET SCHOOL (SKANSKA INTEGRATED SOLUTIONS)
Final Order No Penalty
Case summary
On March 28, 2013, the Region issued an administrative order against Skanska Integrated Solutions, Bacon-Agostini Construction Co., Inc., and K.R. Rezendes, Inc. to correct violations of the NPDES Construction General Permit (CGP) for Storm Water Discharges. Respondents are overseeing development of a new public high school in Somerset, MA. The site is approximately 30 acres in size. In a response to the Administrative Order dated April 26, 2013, Skanska stated in their reponse they are not considered a site Operator , and therefore did not apply for coverage under the GGP. Bacon-Agostini Construction Co., Inc. obtained coverage under the CGP on April 25, 2013. K.R. Rezendes submitted a response regarding a new site concrete washout area, BMP maintenance performed, soil stabilization status/plan, and results of the turbid water investigation. Respondents submitted a new site SWPPP map/BMP plan dated 4/8/13.
Defendants (1)
- SKANSKA INTEGRATED SOLUTIONSNamed in settlement
Facilities (1)
SOMERSET BERKLEY REGIONAL HIGH SCHOOL
625 COUNTY STREET, SOMERSET, MA, 02726
Registry ID: 110054118860
Statutes cited
- CWA 301/402 — NPDES Permit Violations
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
SOMERSET SCHOOL (SKANSKA INTEGRATED SOLUTIONS)entered 2013-03-28
Primary law: CWA
Timeline (2 milestones)
- 2013-02-28Enforcement Action Data Entered
- 2013-03-28Final Order Issued
Case metadata
- EPA activity ID
- 3400059340
- Case number
- 01-2013-2022
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations