EPA v. O'SULLIVAN'S ISLAND SUPERFUND SITE / DERBY CITY OF
Case summary
On December 29, 2014, the Consent Decree for payment of past costs associated with the O?Sullivan?s Island Superfund Site located in Derby, Connecticut was signed by United States Connecticut District Court Judge Warren Eginton. The Consent Decree was signed by the settling parties in October 2014, and lodged with the Court shortly thereafter for a 30 day public comment period during which no comments were received. This settlement was achieved after three years of negotiations between the parties. Under the terms of the Consent Decree, Derby agreed to pay the United States $675,000 by December 31, 2014, or within thirty days of the effective date of the Decree, whichever is later, plus an additional sum for interest on that amount calculated from the effective date of the Decree through the date of payment. In exchange, the United States will provide Derby with a covenant not to sue or take administrative action against it pursuant to Section 107(a) of CERCLA, 42 U.S.C. ? 9607(a), for past response costs incurred at the Site. EPA incurred approximately $4 million in costs to clean up the Site under a CERCLA time-critical removal action performed between 2008 and 2009. Derby is settling in consideration of its limited financial means, as evaluated by EPA as part of a detailed financial analysis of the settling party?s ability to pay past response costs associated with the Site. EPA performed a removal action at the Site several years ago. The City is now working towards re-opening the property for passive recreation, as well as redevelopment for use as a handicap-accessible fishing pier and boat launch.
Defendants (1)
- DERBY CT, CITY OFNamed in complaintNamed in settlement
Facilities (1)
O'SULLIVAN'S ISLAND SUPERFUND SITE
CONFLUENCE OF HOUSATONIC AND NAUGATUCK RIVERS, DERBY, CT, 06418
Registry ID: 110063601437
Statutes cited
- CERCLA 107A — Cost Recovery
Enforcement conclusions (1)
O'SULLIVAN'S ISLAND SUPERFUND SITE / DERBY CITY OFentered 2014-12-30
Primary law: CERCLA
Timeline (5 milestones)
- 2013-07-30Referred To Dept Of Justice
- 2013-09-06Enforcement Action Data Entered
- 2014-10-28Complaint Filed With Court
- 2014-10-28Final Order Lodged
- 2014-12-30Final Order Entered
Case metadata
- EPA activity ID
- 3400153277
- Case number
- 01-2013-0525
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2013-0525 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.