EPA v. SUDBURY MA TOWN OF
Final Order With Penalty
Case summary
On July 18, 2012, Region 1 filed a Clean Water Act Expedited Settlement Agreement under which the Town of Sudbury, Massachusetts agreed to pay a $1,500 penalty for failing to submit and timely submit annual report(s) under the NPDES General MS4 Permit. Sudbury will also complete a supplemental environmental project valued at $5,625 that will upgrade stormwater best management practices in two locations outside of the town�s municipal separate storm sewer system (MS4) urban areas. 3/8/18: The terminology is incorrect. This a prenegotiated settlement for a Stormwater - MS4 action, not an ESA.
Defendants (1)
- SUDBURY MA TOWN OFNamed in complaintNamed in settlement
Facilities (1)
SUDBURY TOWN OF
275 OLD SUDBURY ROAD, SUDBURY, MA, 01776
Registry ID: 110046310611
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
SUDBURY MA TOWN OFentered 2012-07-17
Primary law: CWA
Federal penalty: $1,500 · SEP: $5,625
Timeline (3 milestones)
- 2012-05-31Complaint Filed/Proposed Order
- 2012-06-06Enforcement Action Data Entered
- 2012-07-17Final Order Issued
Case metadata
- EPA activity ID
- 3000026487
- Case number
- 01-2012-2515
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2012-2515 . Bulk data: ICIS-FEC download summary.