Skip to main content
01-2012-2028Administrative - FormalFinal Order IssuedFY 2012· Region 01

EPA v. WAREHAM TOWN OF

Final Order With Penalty

Case summary

3/8/18:The terminology below is incorrect. This is a pre-negotiated settlement for a Stormwater-MS4 action not an ESA On June 15, 2012, Region 1 filed two Expedited Settlement Agreements under which the Town of Mattapoisett, Massachusetts agreed to pay a $750 penalty and the Town of Wareham, Massachusetts agreed to pay a $1,500 penalty for failing to submit and timely submit annual report(s) under the NPDES General MS4 Permit. Mattapoisett will also complete a groundwater monitoring supplemental environmental project (SEP) valued at $2,813 and Wareham will complete a rain barrel purchase and distribution SEP valued at $5,600.

Defendants (1)

  • WAREHAM TOWN OFNamed in complaintNamed in settlement

Facilities (1)

  • WAREHAM W P C F

    6 TONY LANE, WAREHAM, MA, 02571

    Registry ID: 110000732798

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • WAREHAM TOWN OFentered 2012-06-07

    Primary law: CWA

    Federal penalty: $1,500 · SEP: $5,600

Timeline (3 milestones)

  • 2012-02-28Enforcement Action Data Entered
  • 2012-04-24Complaint Filed/Proposed Order
  • 2012-06-07Final Order Issued

Case metadata

EPA activity ID
2600104255
Case number
01-2012-2028
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2012-2028 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.