EPA v. GREEN MOUNTAIN RAILROAD
Final Order With Penalty
Case summary
On April 12, 2012, EPA entered into an expedited settlement agreement with Green Mountain Railroad Tank Farm (Green Mountain) of North Walpole, New Hampshire addressing violations of the Oil Pollution Prevention regulations at 40 C.F.R. Part 112, promulgated under Section 311(j) of the Clean Water Act. EPAs SPCC inspection at Green Mountains facility revealed that the facility did not have a fully implemented SPCC plan. Pursuant to the agreement, Green Mountain paid an $8,000 penalty.
Defendants (1)
- MCINTYRE SERVICESNamed in complaintNamed in settlement
Facilities (1)
GREEN MOUNTAIN RAILROAD TANK FARM
1 MAIN STREET, NORTH WALPOLE, NH, 03609
Registry ID: 110043461483
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
GREEN MOUNTAIN RAILROADentered 2012-04-12
Primary law: CWA
Federal penalty: $8,000
Timeline (4 milestones)
- 2011-11-30Enforcement Action Data Entered
- 2012-04-12Final Order Issued
- 2012-04-12Enforcement Action Closed
- 2012-04-12Complaint Filed/Proposed Order
Case metadata
- EPA activity ID
- 2600077457
- Case number
- 01-2012-2019
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2012-2019 . Bulk data: ICIS-FEC download summary.