Skip to main content
01-2012-1010Administrative - FormalFinal Order IssuedFY 2012· Region 01

EPA v. BOSTIK

Final Order No Penalty

Case summary

Bostik has burned a liquid hazardous waste in its Struthers Wells boiler since 1988. Comprehensive performance testing was conducted in June 2008, March 2009 (for a subset of parameters) and June 2010 (for VOST only). The Administrative order finds that Bostik has not demonstrated compliance with 40 CFR Part 63 Subpart EEE, and orders Bostik to conduct a comprehensive performance test and dioxin/furan testing. Bostik experienced an explosion at their facilty in March 2011, and the facility had discontinued manufacturing operations at that time, with the intention to restart manufacturing in November 2011.

Defendants (1)

  • BOSTIK INCNamed in settlement

Facilities (1)

  • BOSTIK INCORPORATED

    BOSTON STREET, MIDDLETON, TOWN OF, MA, 019490000

    Registry ID: 110000310315

Statutes cited

  • CAA 112DMACT Standards

Enforcement conclusions (1)

  • BOSTIKentered 2011-11-15

    Primary law: CAA

Timeline (2 milestones)

  • 2011-10-20Enforcement Action Data Entered
  • 2011-11-15Final Order Issued

Case metadata

EPA activity ID
2600068817
Case number
01-2012-1010
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
MACT Standards

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2012-1010 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.