EPA v. FITCHBURG WWTF
Final Order No Penalty
Case summary
Administrative Compliance Order requires the City to complete construction of interim phosphorus upgrades to its WWTF by November 30, 2012, and to achieve compliance with a 12-month rolling average interim total phosphorus limit of 0.5 milligrams/liter (mg/l) no later than March 31, 2013. The Order also includes a schedule for completion of construction of a more extensive upgrade of the WWTF by May 31, 2019 and achievement of compliance with the 0.2 mg/l monthly average total phosphorus limit contained in its 2010 Permit by November 30, 2019. The Order further requires the City to design and construct priority sewer separation work in Project Areas CSS 3 and CSS 4. The scopes of these projects are delineated in attachments to the Order
Defendants (1)
- FITCHBURG WWTFNamed in settlement
Facilities (1)
EAST FITCHBURG WWTF
24 LANIDES LANE, FITCHBURG, MA, 01420
Registry ID: 110006618810
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
FITCHBURG WWTFentered 2011-08-08
Primary law: CWA
Timeline (2 milestones)
- 2011-06-07Enforcement Action Data Entered
- 2011-08-08Final Order Issued
Case metadata
- EPA activity ID
- 2600024760
- Case number
- 01-2011-2043
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2011-2043 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.