01-2010-2508Administrative - FormalFinal Order IssuedFY 2010· Region 01

EPA v. FIRST LIGHT POWER RESOURCES INC (NORTHFIELD MOUNTAIN)

Final Order No Penalty

Case summary

DURING MAINTENANCE OF THE NORTHFIELD MOUNTAIN POWER STATION, LARGE QUANTITIES OF SOLIDS ACCUMULATED IN THE SUPPLY TUNNEL. FIRST LIGHT BEGAN DISCHARGING THESE SOLIDS TO THE CONNECTICUT RIVER WITHOUT A NPDES PERMIT. AN ADMINISTRATIVE ORDER WAS ISSUED TO THE COMPANY REQUIRING IT TO IMMEDIATELY CEASE THE DISCHARGE, AND TO DEVELOP A PLAN TO REMOVE ACCUMULATIONS OF THE DISCHARGE SOLIDS THAT HAD SETTLED INTO THE RIVER.

Defendants (1)

  • FIRST LIGHT POWER RESOURCES INCNamed in settlement

Facilities (1)

  • FIRST LIGHT POWER RESOURCES INC

    99 MILLERS FALLS ROAD, NORTHFIELD, MA, 01360

    Registry ID: 110008404155

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • FIRST LIGHT POWER RESOURCES INC (NORTHFIELD MOUNTAIN)entered 2010-08-03

    Primary law: CWA

Timeline (2 milestones)

  • 2010-08-03Final Order Issued
  • 2010-10-07Enforcement Action Data Entered

Case metadata

EPA activity ID
2200019204
Case number
01-2010-2508
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit