EPA v. CONNECTOR PARK HOLDINGS LLC
Final Order With Penalty
Case summary
CONNECTOR PARK HOLDINGS OWNS, AND CRANSHAW CONSTRUCTION IS THE GENERAL CONTRACTOR FOR, A SITE IN LOWELL BEING DEVELOPED FOR A NEW LOWES STORE. THE FACILITY HAS FAILED TO INITIALLY DOCUMENT SITE INSPECTIONS, AND FAILED TO PROPERLY IMPLEMENT SEDIMENT CONTROLS AT TWO LOCATIONS ON THE SITE.
Defendants (2)
- CONNECTOR PARK HOLDINGS LLC (SB)Named in complaintNamed in settlement
- CRANSHAW CONSTRUCTION OF NEW ENGLAND LTD PTNRSNamed in complaintNamed in settlement
Facilities (1)
LOWES OF LOWELL
790 CHELMSFORD STREET, LOWELL, MA, 01852
Registry ID: 110039178788
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
CONNECTOR PARK HOLDINGS LLCentered 2009-09-28
Primary law: CWA
Federal penalty: $3,500
Timeline (4 milestones)
- 2009-09-28Final Order Issued
- 2009-09-28Enforcement Action Closed
- 2009-09-28Complaint Filed/Proposed Order
- 2009-09-29Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 1800028399
- Case number
- 01-2009-2539
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2009-2539 . Bulk data: ICIS-FEC download summary.