Skip to main content
01-2008-2518Administrative - FormalClosedFY 2008· Region 01

EPA v. ACCUFAB IRONWORKS

Final Order With Penalty

Case summary

EPA INSPECTION SHOWED THAT DURING TWO-MONTH PERIOD RESPONDENT DID NOT HAVE REQUIRED STORM WATER PERMIT FOR SITE, DID NOT CONDUCT REQUIRED STORM WATER INSPECTIONS, AND DID NOT ADEQUATELY MAINTAIN THE STORM WATER CONTROLS THAT RESPONDENT HAD INSTALLED FOR THE SITE.

Defendants (1)

  • ACCUFAB IRONWORKS (SB)Named in complaint

Facilities (1)

  • ACCUFAB EXPANSION

    82 SOUTH MAIN STREET, GOSHEN, MA, 01032

    Registry ID: 110037096022

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • ACCUFAB IRONWORKSentered 2008-10-29

    Primary law: CWA

    Federal penalty: $3,000

Timeline (5 milestones)

  • 2008-09-12Complaint Filed/Proposed Order
  • 2008-09-16Enforcement Action Data Entered
  • 2008-10-29Enforcement Action Closed
  • 2008-10-29NPDES Closed
  • 2008-10-29Final Order Issued

Case metadata

EPA activity ID
1400004952
Case number
01-2008-2518
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations