EPA v. YANKEE FIBER CONTROL INC

Final Order No Penalty

Case summary

In March 2008, Yankee Fiber Control, Inc. of East Providence, RI began asbestos abatement work at Brown University - Gardner House located in Providence, RI. Yankee Fiber Control, Inc. did not submit a renovation and demolition notification to EPA at least 10 working days before the asbestos stripping or removal work or any other activity began, which is in violation of Asbestos National Emission Standards for Hazardous Air Pollutants (NESHAP). On April 8, 2008, the Region issued an Immediate Compliance Order to ensure that Yankee Fiber Control take immediate steps to conduct business in full compliance with the Asbestos NESHAP.

Defendants (1)

  • YANKEE FIBER CONTROL INCNamed in settlement

Facilities (1)

  • YANKEE FIBER CONTROL INC

    2 DEXTER RD, EAST PROVIDENCE, RI, 02914

    Registry ID: 110035841952

Statutes cited

  • CAA 112BAsbestos

Enforcement conclusions (1)

  • YANKEE FIBER CONTROL INCentered 2008-04-08

    Primary law: CAA

Timeline (2 milestones)

  • 2008-04-08Final Order Issued
  • 2008-04-16Enforcement Action Data Entered

Case metadata

EPA activity ID
600092319
Case number
01-2008-1507
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
Asbestos

Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2008-1507 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.