EPA v. PRM CONCRETE
Final Order With Penalty
Case summary
On May 14, 2007, an authorized representative of EPA, conducted an SPCC inspection at PRM Concrete Corp.. Although PRM Concrete Corp. stores oil in amounts above the thresholds requiring the preparation and implementation of a SPCC plan under 40 C.F.R. Part 112, it did not have an adequate SPCC plan. Because of the size of the facility and other factors, EPA is utilizing the ESA enforcement tool.
Defendants (1)
- PRM CONCRETE (SB)Named in complaintNamed in settlement
Facilities (1)
PRM CONCRETE CORP
775 SCHOOL ST, PAWTUCKET, RI, 02860
Registry ID: 110004919116
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
PRM CONCRETEentered 2007-10-01
Primary law: CWA
Federal penalty: $3,000
Timeline (4 milestones)
- 2007-09-13Complaint Filed/Proposed Order
- 2007-10-01Final Order Issued
- 2007-10-01Enforcement Action Data Entered
- 2007-10-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 600066144
- Case number
- 01-2007-2541
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2007-2541 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.