EPA v. VALENTI CONSTRUCTION COMPANY INC
Final Order With Penalty
Case summary
THE SITE IS APPROXIMATELY 150 ACRES OF WHICH APPROXIMATELY 3 TO 4 ACRES WERE DISTRIBUTED WITH THE INTENT TO ESTABLISH UP TO 7 RESIDENTIAL LOTS. THERE WAS NO NOTICE OF INTENT FILED AND A STORM WATER POLLUTION PREVENTION PLAN WAS NOT PREPARED FOR THE SITE. NO STORMWATER INSPECTIONS WERE CONDUCTED. THERE WERE NO BEST MANAGEMENT PRACTICES IMPLEMENTED AT THE SITE. THERE WERE ALSO NO SILT FENCES, HAY BALES, OR OTHER STORMWATER STRUCTURAL CONTROLS INSTALLED AT THE SITE.
Defendants (1)
- VALENTI COSTRUCTION COMPANY INC (SB)Named in complaintNamed in settlement
Facilities (1)
BROOKS STATION RD
MAP 15 PARCEL 5, PRINCETON, MA, 01541
Registry ID: 110024570613
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
VALENTI CONSTRUCTION COMPANY INCentered 2006-12-20
Primary law: CWA
Federal penalty: $7,150
Timeline (4 milestones)
- 2006-12-20Enforcement Action Closed
- 2006-12-20Final Order Issued
- 2006-12-20Complaint Filed/Proposed Order
- 2006-12-28Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 600023294
- Case number
- 01-2007-2504
- Lead agency
- EPA
- EPA region
- 01
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2007-2504 . Bulk data: ICIS-FEC download summary.