Skip to main content
01-2004-0002Administrative - FormalFinal Order IssuedFY 2004· Region 01

EPA v. BROADBROOK MILL SUPERFUND SITE

Final Order With Specified Cost Recovery

Case summary

THIS IS A PROPOSED ADMINISTRATIVE SETTLEMENT FOR RECOVERY OF PAST AND FUTURE RESPONSE COSTS CONCERNING THE BROAD BROOK MILL SUPERFUND SITE IN EAST WINDSOR, CT, WITH HAMILTON SUNDSTRAND CORP ( SETTLING PARTY ). THE SETTLEMENT REQUIRES THE SETTLING PARTY TO PAY $322,301.88 IN REIMBURSEMENT OF PAST RESPONSE COSTS, AND PAY ALL FUTURE RESPONSE COSTS NOT INCONSISTENT WITH THE NATIONAL CONTINGENCY PLAN ON A PERIODIC BASIS TO THE EPA HAZARDOUS SUBSTANCE SUPERFUND.

Defendants (1)

  • HAMILTON SUNSTRAND CORPNamed in complaintNamed in settlement

Facilities (1)

  • BROAD BROOK MILL

    110,112 MAIN ST AND 1-21 BROOKSIDE DRIVE, EAST WINDSOR, CT, 06016

    Registry ID: 110009271297

Statutes cited

  • CERCLA 122HAdministrative Cost Recovery Settlement

Enforcement conclusions (1)

  • BROADBROOK MILL / HAMILTON SUNDSTRAND CORPentered 2003-12-05

    Primary law: CERCLA

Timeline (3 milestones)

  • 2003-12-05Complaint Filed/Proposed Order
  • 2003-12-05Final Order Issued
  • 2003-12-16Enforcement Action Data Entered

Case metadata

EPA activity ID
109295
Case number
01-2004-0002
Lead agency
EPA
EPA region
01
Voluntary self-disclosure
No
Primary statute
Administrative Cost Recovery Settlement