EPA v. AMERICAN PREMIER UNDERWRITERS ET AL /RAILROAD DEPOT SUPERFUND SITE
Final Order With Specified Cost Recovery
Case summary
'CIVIL REFERRAL PROPOSING THE FILING OF A CIVIL ACTION AGAINST THE PARTIES TO RECOVER THE UNITED STATES'' RESPONSE COSTS TOTALLING $1,268,873.99, PLUS APPROXIMATELY $176,137.86 IN INTEREST. COSTS WERE INCURRED BY THE FEDERAL GOVERNMENT IN CONDUCTING A CERCLA REMOVAL ACTION AT THE SITE IN 1997-1998 AND CARRYING OUT SUBSEQUENT NEGOTIATIONS WITH THE PARTIES.'
Defendants (4)
- AMERICAN PREMIER UNDERWRITERSNamed in complaintNamed in settlement
- CONSOLIDATED RAIL CORPORATIONNamed in complaintNamed in settlement
- NEW BEDFORD, CITY OFNamed in complaintNamed in settlement
- HOUSING 70 CORPORATIONNamed in complaintNamed in settlement
Facilities (1)
RAILROAD DEPOT
ROUTE 18, NEW BEDFORD, MA, 02741
Registry ID: 110009331008
Statutes cited
- CERCLA 107A — Cost Recovery
Enforcement conclusions (1)
AMERICAN PREMIER UNDERWRITERS / RAILROAD DEPOTentered 2003-10-16
Primary law: CERCLA
Timeline (6 milestones)
- 2002-09-30Referred To Dept Of Justice
- 2002-10-03Enforcement Action Data Entered
- 2003-07-25Final Order Lodged
- 2003-07-25Complaint Filed With Court
- 2003-10-16Concluded
- 2003-10-16Final Order Entered
Case metadata
- EPA activity ID
- 86414
- Case number
- 01-2002-0142
- Lead agency
- EPA
- EPA region
- 01
- Primary statute
- Cost Recovery
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-2002-0142 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.