EPA v. GREEN MOUNTAIN POWER CORP (PINE ST CANAL)
Final Order With Specified Cost Recovery
Cost recovery
$5,250,000
Compliance action
$6,895,000
Case summary
THE PRPS HAVE AGREED TO PERFORM THE REMEDIAL DESIGN/ REMEDIAL ACTION FOR THE PINE STREET SITE; PAY $5.25 MILLION PLUS. INTEREST ON PAST RESPONSE COSTS; PAY 100% OF EPA'S OVERSIGHT OF THE RD/RA; AND PERFORM NATURAL RESERVE DAMAGE COMPENSATION PROJECTS.
Defendants (1)
- GREEN MOUNTAIN POWER CORPNamed in complaintNamed in settlement
Facilities (1)
GREEN MOUNTAIN POWER ET
PINE ST, BURLINGTON, VT, 05401
Registry ID: 110009259809
Statutes cited
- CERCLA 107 — Superfund
Enforcement conclusions (1)
GREEN MOUNTAIN POWER COMPANYentered 2000-02-11
Primary law: CERCLA
Timeline (6 milestones)
- 1999-09-30Referred To Dept Of Justice
- 1999-10-05Enforcement Action Data Entered
- 1999-11-23Final Order Lodged
- 1999-11-23Complaint Filed With Court
- 2000-02-11Final Order Entered
- 2000-02-11Concluded
Case metadata
- EPA activity ID
- 1103
- Case number
- 01-1999-0114
- DOJ docket
- 90-113-409A
- Lead agency
- EPA
- HQ division
- CER
- Branch
- CERC
- EPA region
- 01
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Superfund
Sourced verbatim from EPA ECHO Enforcement Case Report for case 01-1999-0114 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.