49 CFR § 1250.4Chapter X

§ 1250.4 Rail infrastructure projects reporting.

Primary source

Verbatim text below is from the Electronic Code of Federal Regulations (eCFR), a public-domain U.S. government work. Always verify the current version with the eCFR before relying on it for any legal matter.

Full Text

(a) Class I railroads shall submit annually a narrative report of significant rail infrastructure projects that will be commenced during the current calendar year, and a six-month update on those projects. The reports should briefly describe each project, its purpose, location (state/counties), and projected date of completion.

(b) A “significant rail infrastructure project” is defined as a project with anticipated expenditures of $75 million or more over the life of the project.

(c) The narrative report should be submitted no later than March 1 of each calendar year and the update no later than September 1 of each calendar year via email to the Board's Office of Public Assistance, Governmental Affairs and Compliance (OPAGAC) via the method and in the form prescribed by OPAGAC. In the event that March 1 or September 1 is a Federal holiday, weekend, or falls on a day when STB offices are closed for any other reason, then the data should be reported on the next business day when the offices are open. ,

eCFR data current as of: June 10, 2026