§ 354.2 Scope of this regulation.
Primary source
Verbatim text below is from the Electronic Code of Federal Regulations (eCFR), a public-domain U.S. government work. Always verify the current version with the eCFR before relying on it for any legal matter.
Full Text
The regulation in this part applies to all persons or licensees who have applied for or have received from the NRC:
(a) A license to construct or operate a commercial nuclear power plant;
(b) A possession-only license for a commercial nuclear power plant, with the exception of licensees that have received an NRC-approved exemption to 10 CFR 50.54(q) requirements;
(c) An early site permit for a commercial nuclear power plant;
(d) A combined construction permit and operating license for a commercial nuclear power plant; or
(e) Any other NRC licensee that is now or may become subject to requirements for offsite radiological emergency planning and preparedness.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.