§ 14.18 Restoration and reclamation.

Primary source

Verbatim text below is from the Electronic Code of Federal Regulations (eCFR), a public-domain U.S. government work. Always verify the current version with the eCFR before relying on it for any legal matter.

Full Text

(a) After expiration or termination of the right-of-way permit, the permittee must restore or reclaim the permitted area to standards directed and approved by the NPS.

(b) If restoration or reclamation is not completed within a reasonable time or in accordance with a schedule established in a special use permit for the restoration and reclamation activities, the permittee will be liable to the NPS for all costs of restoring and reclaiming the permitted area undertaken by the NPS, or its contractor, to the satisfaction of the NPS. This obligation will survive the termination or expiration of a right-of-way permit.

eCFR data current as of: June 10, 2026

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.