33 CFR § 114.45Chapter I

§ 114.45 Applications, extensions of time.

Primary source

Verbatim text below is from the Electronic Code of Federal Regulations (eCFR), a public-domain U.S. government work. Always verify the current version with the eCFR before relying on it for any legal matter.

Full Text

Extensions of time to commence or complete construction of a bridge or remove a bridge that has been replaced as an element of a permitted bridge project must be submitted to, and received by the District Commander at least 30 days before the existing permit expires to allow the permit to remain in effect until the final agency action is taken.

(33 U.S.C. 401, 491, 525, 535; 49 CFR 1.46(c) (8), (9), (10), (q))

[CGD 76-144, 42 FR 28882, June 6, 1977]