Zeigler v. Blount Bros. Const. Co.

Citations

  • 364 So. 2d 1163
  • 1978 Ala. LEXIS 1809

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • power company rate-paying subscribers were not third-party beneficiaries of a contract between Alabama Power Company and Blount Brothers whereby the latter negligently constructed a dam for the former
  • construction firm cannot foresee utility rate increases due to failure of a dam
  • construction firm cannot foresee utility rate increases due to failure of a dam