Young v. Smith
Citations
- 202 Pa. 329
- 51 A. 890
Syllabus
<p>Contract — Building contract — Reservation of advances for subcontractor.</p> <p>Where the agents oí an owner of ground rents have agreed to reserve for a subcontractor certain sums out of moneys which were to be advanced to a contractor for a building operation, and the contractor fails before the completion of the operation, and consequently does not become entitled to certain instalments of the advances, the subcontractor although he has completed his part of the work, cannot recover from the agents the portion of these instalments which they had agreed to reserve for him.</p>
Judges: Brown, Dean, Fell, McCollum, Mestrezat