· 6/1/2010
WEST CENTRAL CONCRETE, LLC v. Reeves
Citations
- 310 S.W.3d 778
- 2010 Mo. App. LEXIS 740
- 2010 WL 2160778
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- citing Hennis v. Tucker, 447 S.W.2d 580, 583 (Mo. App. 1969)) (citing to the old version of Rule 53.01
- “Section 429.170 requires an action to enforce a mechanic's lien ‘shall be commenced within six months after filing the lien, and prosecuted without unnecessary delay.’” Id. (italics in original)
- whether a party failed to diligently prosecute a mechanic’s lien action and joinder
Source: CourtListener parenthetical corpus (CC0).
Judges: Mitchell, Hardwick, Martin
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.