WEST CENTRAL CONCRETE, LLC v. Reeves

Citations

  • 310 S.W.3d 778
  • 2010 Mo. App. LEXIS 740
  • 2010 WL 2160778

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • citing Hennis v. Tucker, 447 S.W.2d 580, 583 (Mo. App. 1969)) (citing to the old version of Rule 53.01
  • “Section 429.170 requires an action to enforce a mechanic's lien ‘shall be commenced within six months after filing the lien, and prosecuted without unnecessary delay.’” Id. (italics in original)
  • whether a party failed to diligently prosecute a mechanic’s lien action and joinder

Source: CourtListener parenthetical corpus (CC0).

Judges: Mitchell, Hardwick, Martin