Waggoner Motors, Inc. v. Waverly Church of Christ

Citations

  • 159 S.W.3d 42
  • 2004 Tenn. App. LEXIS 604
  • 2004 WL 2083712

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • noting that appellant “church, acting as its own general contractor, began constructing a 9,000-square-foot general purpose building in back of its existing building”
  • discussing lost profits in the context of the sale of goods
  • “[D]amages become too speculative only when the existence of damages is uncertain, not when the precise amount is uncertain.”
  • “The amount of lost profits damages may be based on estimates.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Koch, Cottrell