· 2/19/1986
Vanater v. Tom Lilly Const.
Citations
- 483 So. 2d 506
- 11 Fla. L. Weekly 459
- 1986 Fla. App. LEXIS 6481
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- reversing trial court’s improper limitation of recovery to the cost to cure the defects
- court found that contractor was liable for the full cost of replacing particle board shelves where contract called for wood
- “Where a contractor breaches a contract by failing to complete an improvement, the owner is entitled to damages for delay in completion measured by its rental value during the period of delay.”
- “Where a contractor breaches a contract by failing to complete an improvement, the owner is entitled to damages for delay in completion measured by its rental value during the period of delay.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Boardman
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.