· 3/4/1975
United States v. ELLIS CONSTRUCTION CO., INC.
Citations
- 398 F. Supp. 719
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- party was a material-man who custom manufactured steel items for the project and whose contribution to the total cost of improvement was less than 9 percent, which was not a sufficiently large and definable part of the project
- 9% of total construction cost
Source: CourtListener parenthetical corpus (CC0).
Judges: Neese
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).