· 10/29/1991

Federal Case

Citations

  • 942 F.2d 946

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • concluding that a subcontractor cannot recover from a Miller Act surety the profits on out-of-pocket expenditures attributable to delay. A claim for profit does not involve actual outlay and thus “falls outside both the letter and the spirit of the [Miller] Act.”
  • subcontractor allowed to recover when delay resulted from government change orders
  • subcontractor allowed to recover when delay resulted from government change orders

Source: CourtListener parenthetical corpus (CC0).

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).