United States For The Use And Benefit Of Walton Technology, Inc. v. Weststar Engineering, Inc.
Citations
- 290 F.3d 1199
- 2002 Cal. Daily Op. Serv. 4405
- 2002 Daily Journal DAR 5643
- 2002 U.S. App. LEXIS 9605
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- noting that a waiver of Miller Act rights must be “clear and explicit”
- dismissing unjust 6 enrichment claim where plaintiff had affirmed the validity of the contract
- “A subcontractor’s right of recovery on a Miller Act payment bond accrues ninety days after the subcontractor has completed its work, not ‘when .and if the prime contractor is paid by the government.”