United States ex rel. Great Lakes Plumbing & Heating Co. v. Orr Construction Co.
Citations
- 560 F.2d 765
- 1977 U.S. App. LEXIS 12061
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “Even if in the resolution of that dispute Honeywell was found to be due something less than its claim, the notice may still have been substantially accurate, for the statute does not require precision.”
- “The principal purpose of the Miller Act is the protection of persons supplying labor and materials to subcontractors on federal construction projects. To that end, the Supreme Court has held that the Miller Act should receive a liberal construction.”
- contents of notice sufficient if “substantially accurate”
- strictly enforcing statutory notice requirement
Source: CourtListener parenthetical corpus (CC0).
Judges: Swygert
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.