Union Iron Works v. Gray & Son
Citations
- 126 Wash. 290
- 218 P. 8
- 1923 Wash. LEXIS 1148
Syllabus
<p>Sales (159, 165) — Set-off in Action fob Pbice — Damages Not Contemplated. Upon a sale of mill machinery, the purchaser cannot claim a set-off for delay, which caused an added expense of re-handling logs on account of the small capacity of the mill pond, where the seller was not informed of this situation.</p> <p>Same (159, 165). Upon a sale of mill machinery, the purchaser cannot claim a set-off for delay causing the loss of ■ contemplated profits upon a certain contract to supply timber, which contract was filled after the mill resumed operations.</p>
Judges: Touvian