· 3/10/1992
Triax-Pacific, a Joint Venture v. Michael P.W. Stone, Secretary of the Army
Citations
- 958 F.2d 351
- 37 Cont. Cas. Fed. 76,275
- 1992 U.S. App. LEXIS 3854
- 1992 WL 43319
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that a contractor could not recover where a delay was caused, in part, by the contractor’s failure to timely complete prior projects
- “[A] contractor may recover for an unreasonable delay, if the Government is ‘the sole proximate cause of the contractor’s additional loss, and the contractor would not have been delayed for any other reason during that period.’ ”
Source: CourtListener parenthetical corpus (CC0).
Judges: Clevenger, Lourie, Michel
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).