Skip to main content
· 6/11/1993

Town of Chesapeake Beach v. Pessoa Construction Co.

Citations

  • 625 A.2d 1014
  • 330 Md. 744
  • 1993 Md. LEXIS 92

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that the existence of an agreement to arbitrate is necessarily a preliminary matter and so a trial court ruling requiring arbitration must be immediately appealable because “judicial review of an award following arbitration is limited.”
  • stating that a petition to compel arbitration can be filed as a separate action
  • addressing whether an order denying a stay of arbitration is reviewable under the collateral order doctrine
  • “If the parties are incorrectly forced into the wrong forum, the loss to each may be significant.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Murphy, Eldridge, Rodowsky, McAuliffe, Chasanow, Karwacki, Orth

Read full opinion on CourtListener