Tobey v. Price
Citations
- 75 Ill. 645
Syllabus
<p>Contract — right of contractor to damages for icing delayed in his worh. Where a person employed to furnish all necessary labor and materials, and do every thing specified under the head of mason’s work, etc., in the erection of a building, the iron work and stone cutters’ work to be furnished by the employer, is delayed in the completion of his contract by the delay of the' employer in furnishing the iron work and cut stone, he will be entitled to recover damages occasioned by the delay, and such damages will not be waived by continuing the work until the completion of his contract..</p>
Judges: Breese