Tennessee Gas Pipeline v. 104 Acres in Prov. Cty.

Citations

  • 749 F. Supp. 427
  • 1990 U.S. Dist. LEXIS 14600

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that “requirements in the FERC order arise after ownership of the rights of way are obtained and do not operate as a shield against the exercise of eminent domain power”
  • holding that “requirements in the FERC order arise after ownership of the rights of way are obtained and do not operate as a shield against the exercise of eminent domain power”
  • noting the “line of decisions holding that landowners have no due process right to notice and a hearing in agency proceedings to determine the need for condemnation”
  • “Disputes over the validity of the certificate based on FERC’s failure to require compliance with the [CWA] or state law must be brought to the Commission for rehearing.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Boyle

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.