· 6/30/1998
Tennessee Gas Pipeline Co. v. New England Power
Citations
- 6 F. Supp. 2d 102
- 1998 U.S. Dist. LEXIS 9954
- 1998 WL 372962
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- granting motion for partial summary judgment where the condemnor satisfied the elements of Section 717f(h)
- granting motion for partial summary judgment where the condemnor satisfied the elements of Section 717f(h)
- granting motion for partial summary judgment where the condemnor satisfied the elements of Section 717f(h)
- “[I]nterference with pipeline company’s use of land would irreparably harm it and [the] public by likely preventing project completion before FERC-imposed deadline.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Lasker
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).