Systems Development Corp. v. McHugh

Citations

  • 658 F.3d 1341
  • 2011 U.S. App. LEXIS 19604
  • 2011 WL 4435990

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • \Contractor compliance with [the] statutory time limit on the presentment of a claim to a [contracting officer] is a jurisdictional prerequisite for any subsequent appeal\
  • contractor compliance with the 6-year statutory time limit on the presentment of a claim to a CO is a jurisdictional prerequisite for any subsequent appeal of the CO's decision on that claim
  • contractor compliance with the six-year statutory time limit on the presentment of a claim to a CO is a jurisdictional prerequisite for any subsequent appeal of the CO's decision on that claim
  • contractor compliance with the 6 year statutory time limit on the presentment of a claim to a CO is a jurisdictional prerequisite for any appeal ofthe CO's decision (or lack of a decision) thereon

Source: CourtListener parenthetical corpus (CC0).

Judges: Newman, Prost, O'Malley

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).