Sweeney v. Lewis Construction Co.

Citations

  • 66 Wash. 490
  • 119 P. 1108
  • 1912 Wash. LEXIS 792

Syllabus

<p>Corporations — Representations—Contract — Individual Liability oe Oeeicers. The evidence sufficiently shows that a contract was made by the plaintiff direct with a corporation, rather than with its officers individually, where negotiations were carried on in the name of the corporation and plaintiff’s offer and letters wbre addressed to it.</p> <p>Contracts — Regrade oe Lots — Waiver oe Damages — Construction. A contract waiving damages from a regrade about to be made, contemplates only future damages, where there was evidence that no substantial damages had theretofore been sustained and no claim had been made therefor.</p> <p>Contracts — Regrade of Lots — Breach—Measure of Damages. Under a contract waiving damages to property from a contemplated regrade, to be completed within a specified time, on breach of the contract upon its becoming impossible to complete the regrade within the time, the work being abandoned, measure of damages to be recovered by the property owners is the difference in the value of the lots before the commencing of the work and their value when work was suspended, eliminating changes in market values, together with damages to buildings and loss of rentals; and not the cost of completing the work irrespective of the value of the property.</p>

Judges: Crow

Read full opinion on CourtListener

Cited by

3 cases in this archive cite this case.

Cites

3 cases in this archive are cited by this case.

Other cases named Sweeney v. Lewis Construction Co.

1 other CourtListener record shares this case name.

Sourced from CourtListener / Free Law Project (CC0).