Skip to main content
· 4/7/1965

Steele v. ADH Building Contractors, Inc.

Citations

  • 174 So. 2d 16

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • modification should be allowed on ground of change of condition in that the accord was based on claimant's then current condition, while the progress of the injury not realized or anticipated might, at a later time, develop into a different condition

Source: CourtListener parenthetical corpus (CC0).

Judges: Thomas

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.