State Ex Rel. Santa Fe Sand & Gravel Co. v. Pecos Construction Co.
Citations
- 519 P.2d 294
- 86 N.M. 58
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- finding that subcontractor was unable to recover for extra work because the subcontractor had to “obtain written authorization” for such compensation “which was never secured”
- enforcing contract’s requirement that compensation for extra work be obtained through written authorization
- “The meaning of a contract is to be determined and construed with reference to the intention of the parties at the time the contract was made.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Martinez, McManus, Oman
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).