Star Manufacturing, Inc. v. Edenfield

Citations

  • 382 S.E.2d 706
  • 191 Ga. App. 665
  • 1989 Ga. App. LEXIS 772

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • affidavit, dated and sworn to on date of receipt of final payment, held sufficient to dissolve lien
  • contractor’s affidavit held sufficient to dissolve subcontractor’s lien because affidavit had been given in conjunction with contractor’s receipt of final payment (OCGA § 44-14-361.2 (a) (2) (B) (iii)) and no lien had been filed at the time of payment to contractor
  • contractor's affidavit held sufficient to dissolve subcontractor's lien because affidavit had been given in conjunction with contractor's receipt of final payment (OCGA § 44-14-361.2 (a) (2) (B) (iii)) and no lien had been filed at the time of payment to contractor
  • any error in supplementation of record was harmless
  • any error in supplementation of record was harmless

Source: CourtListener parenthetical corpus (CC0).

Judges: Birdsong, Been, Benham

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).